Adapt supplied 6,000 m² of panel decking for the Battersea project, which had an overall project value of approximately £1 billion.The decking arrangement allowed panels to be removed without relying on the crane. It also avoided trapping panels within the structure behind perimeter tables, supporting the contractor’s preferred construction sequence.The customer reported that the project finished ahead of programme and credited the panel decking system as a significant contributor. This project demonstrates Adapt’s capacity to supply slab formwork equipment at scale.
This building was to become the longest in Europe and was the UKs largest mixed use construction project. The bespoke solution that only Adapt could offer allowed all panel decking without infills or perimeter tables needed. Achieved by creating triangular panels to allow the snake shape on plan view