This project consisted of a fully automatic climbing system both inside and out.

Project Overview

This project consisted of a fully automatic climbing system both inside and out but with the flexibility of allowing platforms to lift independently.

Lifting platforms independently, rather than as a whole allowed the site to continue the working cycle and steel fixing as they went. With only one live anchor the customer achieved a 50% saving in this area along with more working space and a full enclosure of the core with light allowed through the edge protection with the 2mm holes in the cladding so you can see through.

  • Duration: 40 Weeks
  • 27 Levels
  • Hydraulic Climbing Core Formwork