HomeCase Studies
Park Lane Liverpool

Park Lane Liverpool

Adapt supplied concrete frame formwork equipment for the Park Lane project in Liverpool, which had an overall project value of £60 million.The project forms part of Adapt’s experience in supplying formwork for reinforced concrete construction in the North West and across the UK.

Project Overview

This system was chosen because of its ultra flexibility. It’s the lightest panel decking system on the market and most efficient as the grid stands alone from the panels effectively speeding up assembly by 35%. Huge savings available with this system. This customer bought the kit in the end and moved over to another 9 storey frame in Newcastle after that.

  • Duration: 20 weeks
  • Levels: 9
  • Formwork: Panel Decking Formwork